Fenland Inspire! Civil Parking Enforcement Update

21/07/2025 - Fenland Inspire! Civil Parking Enforcement Update

AGREED to:

 

·         Note the updated estimated increase in the overall project delivery costs, timelines and CPE running costs post implementation.

·         Consent to officers proceeding with obtaining updated corrective works costs from Milestone which is likely in itself to incur a cost (currently unknown but estimated to be within the range of £50k to £100k).

·         Consent to officers proceeding with the implementation of CPE based on the predicted costs contained within this update report in advance of obtaining actual costs. Estimated costs to be brought back to Cabinet for approval upon receipt.

·         Provide an officer steer on any previously highlighted red line areas within the previously drafted preliminary agency agreement.

·         Approve the member/officer CPE project team to agree any red line areas in order to progress the CPE project to implementation. This would include the administration of all highway permits, suspensions, waivers and dispensations.